Wednesday, September 29, 2010

We are making power!

Today was the big day, around 10 AM this morning, the solar panels on the roof of Copyquik Printing  in Hagerstown started producing power! Of course it was cloudy and gray most of the day, so the system only produced about 25% of its rated capacity, but we are connected!

We all watch...


...as Andy starts the system.




Friday, September 24, 2010

Solar panel wiring



Pulling wires from the solar panels
 
This week, the wiring was completed connecting the solar panels into our electrical panel. Next step is an electrical inspection. If all goes well, we can start producing power next week!


Connecting into our main panel


 




Thursday, September 16, 2010

Solar Panels are installed

Steve and Phil Kelly inspecting the completed install.
The installation of all 142 solar panels is complete! The next step is to connect the wiring from the solar panels to our electrial panel.